Grid interconnection Market Outlook 2026–2034: Growth Drivers, Key Companies, Strategic Developments & Adoption Forecast — A Meticulous Next™ Foresight Brief
What This Brief Covers
This Meticulous Next™ brief examines grid interconnection, meaning the studies, agreements and network upgrades that a power plant, storage project or large electricity user must complete before it connects to the grid. It tests whether federal rules, cluster studies and automated study tools turn the interconnection queue from a bottleneck into a routine process, and which participants capture value among grid operators, software providers, engineering firms and developers.
The queue is very large and moves slowly. Lawrence Berkeley National Laboratory counted 2,061 GW of active capacity in 8,244 requests in the United States at the end of 2025, down 10% from a year earlier, yet only 53 GW out of the 2,290 GW active in the 2024 queue reached operation during 2025, about 2%. The conclusion is that a request is far more likely to be withdrawn than built, so queue size overstates the capacity that will be added.
Time is the main cost. Projects built in 2025 took a median of 61 months from request to commercial operation, against 36 months in 2015, and of requests made from 2000 to 2020 only 19% by number reached operation while 71% were withdrawn. The conclusion is that developers plan around long and uncertain timelines, which raises financing costs and favours projects that are ready early.
The mix of the queue is shifting. Gas capacity in the queue rose 86% to 253 GW during 2025 while solar fell 19% to 773 GW, storage fell 16% to 749 GW and wind fell 19% to 220 GW. In PJM, 51 projects totalling 9,361 MW of unforced capacity were selected in May 2025 for fast-track studies, most of them gas. The conclusion is that urgent demand for firm capacity is pulling gas projects ahead of renewable projects through the queue.
The brief treats grid interconnection as a high-impact signal with an eight year horizon to 2034. It identifies which reforms, tools and regions clear the queue first and what each means for utilities, developers and software and engineering providers. It is a focused 101-page decision brief that presents an indicative trajectory rather than a segmented market model.
| Parameter | Details |
|---|---|
| Forward horizon | 2026–2034 (8 years) |
| Emerging force | Grid interconnection: federal reform, cluster studies and automated study tools for clearing interconnection queues |
| Technology readiness | Cluster study processes adopted or in transition at most balancing areas; automation and AI study tools in pilot at MISO, SPP, PJM, CAISO and ISO New England |
| Indicative market size & forecast | The grid interconnection market, covering interconnection study and queue management software, study and engineering services and process automation, and excluding network upgrade construction, generation equipment and transmission hardware, is valued at USD 1.2–1.8 billion in 2026 and is projected to reach USD 2.77–4.15 billion by 2034, at a CAGR of 11% |
| Mainstream inflection | ~2030, when cluster studies and automated tools deliver study results within set deadlines and median time to operation falls below the 2015 level of 36 months |
| Signal strength | High-impact: a queue of 2,061 GW with only 2% reaching operation in 2025, a median of 61 months to operation and automation pilots at five operators |
| Primary beneficiaries | Study software and engineering providers; developers with ready projects and site control; operators with automated processes |
| Brief length / format | 101 pages · PDF + executive summary deck · instant delivery |
Understanding the Technology
A generation, storage or large load project asks the grid operator to study how it would affect the network. The operator tests the connection, identifies the upgrades needed and sets the cost, after which the project signs an agreement and builds its connection. Under older rules requests were studied one at a time, which meant a change in one project forced restudies of those behind it.
Cluster studies group requests and study them together in batches. Order No. 2023 of the Federal Energy Regulatory Commission, issued on 28 July 2023, set a 150-day cluster study, larger study deposits, site control of 90% at submission and penalties for withdrawal and for missed study deadlines.
Automation tools run power flow and screening studies faster. A pilot of SUGAR software from Pearl Street Technologies at MISO reportedly cut study time by 98%, SPP works with Hitachi on an artificial intelligence tool and with GridUnity on process automation, and PJM works with Alphabet on readiness review.
Uses are generator and storage interconnection, large load connection for data centres and factories, and queue management and reporting for utilities and developers.
The limits are study staffing, data quality, withdrawals that force restudies, delays in studies of affected neighbouring systems and the cost of network upgrades. The period turns on whether cluster studies and automation shorten the median time to operation.
Market Outlook
The grid interconnection market, covering interconnection study and queue management software, study and engineering services and process automation, and excluding network upgrade construction, generation equipment and transmission hardware, is valued at USD 1.2–1.8 billion in 2026 and is projected to reach USD 2.77–4.15 billion by 2034, at a CAGR of 11%.
The 2026 base rests on study and queue management software, study and engineering services and process automation at grid operators and utilities in the United States, plus early activity in other markets. Growth then follows the shift to cluster studies, wider use of automation and the creation of processes for large loads.
The forecast is sensitive to rule changes at the Federal Energy Regulatory Commission, withdrawal rates, operator staffing and the volume of data centre load requests. Regionally, the United States holds nearly all of the base, and other markets grow from a smaller base as they reform their own queues.
Scenarios
The base case assumes cluster studies are completed on schedule, automation spreads beyond pilots and withdrawals fall as deposits and readiness rules take effect, so that study results arrive within set deadlines by 2030. An accelerated case assumes fast adoption of automation and a smaller number of speculative requests, bringing the inflection to 2028 and lifting the 2034 value to the top of the range. A delayed case assumes staffing shortages, restudies and large load surges, moving the inflection to 2033 and holding growth at the bottom of the range.
Factors Behind Growth
Growth drivers
- Electricity demand growth.
- Renewable and storage build-out.
- Federal and state reform.
- Resource adequacy needs.
Enablers
- Cluster study rules.
- Study automation software.
- Fast-track processes.
- Heatmaps and data access.
Restraints and barriers
- Study backlogs and staffing.
- Withdrawals and restudies.
- Network upgrade cost and delay.
- Affected system study delays.
The Forces at Play
The direction of grid interconnection is set by federal rules on interconnection, automation of studies, large load growth from data centres, fast-track paths for resource adequacy and the allocation of network upgrade costs.
Adoption Outlook
How the shift is likely to unfold across three time horizons.
Operators complete the move to cluster studies and roll out automation pilots.
Legacy queues clear and large load processes are set up at regional transmission organisations.
Interconnection becomes a routine, largely automated process.
Latest Strategic Developments
| Date | Development | Type | Significance |
|---|---|---|---|
| Jul 2023 | The Federal Energy Regulatory Commission issues Order No. 2023, requiring cluster studies, larger deposits, site control and penalties for missed study deadlines | Federal rule | Sets the national basis for first-ready, first-served interconnection |
| May 2024 | Compliance filings for Order No. 2023 fall due after extensions from the original December 2023 date | Compliance deadline | Moves operators to the new process |
| May 2025 | PJM selects 51 projects totalling 9,361 MW of unforced capacity under its Reliability Resource Initiative, from 94 applications | Fast-track selection | Shows urgent demand for firm capacity, mostly gas, moving ahead in the queue |
| Jun 2026 | Lawrence Berkeley National Laboratory publishes Queued Up 2026, showing 2,061 GW active at the end of 2025 and 53 GW reaching operation during the year | Queue report | Quantifies the backlog and the low completion rate |
| Jun 2026 | The Federal Energy Regulatory Commission opens six show-cause proceedings requiring grid operators to explain how they will speed large load interconnection | Regulatory proceeding | Extends interconnection reform to data centres and factories |
Key Players & Competitive Landscape
The key participants in grid interconnection include PJM Interconnection, L.L.C., Midcontinent Independent System Operator, Inc., Southwest Power Pool, Inc., California Independent System Operator Corporation, Electric Reliability Council of Texas, Inc., ISO New England Inc., New York Independent System Operator, Inc., Federal Energy Regulatory Commission, Lawrence Berkeley National Laboratory, Hitachi, Ltd., Alphabet Inc., Pearl Street Technologies, Inc., GridUnity, Inc., Burns & McDonnell Engineering Company, Inc., Black & Veatch Holding Company, Quanta Services, Inc., Duke Energy Corporation, NextEra Energy, Inc., American Electric Power Company, Inc., Berkshire Hathaway Energy Company, Dominion Energy, Inc., The Southern Company, Xcel Energy Inc., Entergy Corporation, Exelon Corporation, Edison International, PG&E Corporation, Vistra Corp., Invenergy LLC, The AES Corporation, Microsoft Corporation, Amazon.com, Inc., Meta Platforms, Inc., Equinix, Inc., Digital Realty Trust, Inc., U.S. Department of Energy, North American Electric Reliability Corporation, American Clean Power Association, Solar Energy Industries Association and Electric Power Research Institute, Inc.
The brief profiles representative participants in each archetype and assesses which are positioned to lead as queues move to cluster studies and automated tools.
The seven regional grid operators control the process in their regions, Pearl Street Technologies, GridUnity and Hitachi lead among the providers of study and automation tools, and Burns & McDonnell and Black & Veatch lead among engineering firms. Competitive intensity is rising among software providers as operators move from pilots to contracts, and is low among operators, which each hold a regional monopoly on their process.
| Archetype | Representative players | Position in 2026 | Outlook to 2034 |
|---|---|---|---|
| Grid operators | PJM Interconnection, Midcontinent Independent System Operator, Southwest Power Pool, California Independent System Operator, Electric Reliability Council of Texas, ISO New England, New York Independent System Operator | Interconnection process and studies | Run queues and studies |
| Study software and automation providers | Pearl Street Technologies, GridUnity, Hitachi, Alphabet | Study and process automation | Supply tools that speed studies |
| Engineering and construction firms | Burns & McDonnell Engineering, Black & Veatch, Quanta Services | Studies, design and upgrade construction | Perform studies and build upgrades |
| Utilities and transmission owners | Duke Energy, NextEra Energy, American Electric Power, Berkshire Hathaway Energy, Dominion Energy, The Southern Company, Xcel Energy, Entergy, Exelon, Edison International, PG&E, Vistra | Transmission ownership and upgrades | Own the network and build upgrades |
| Developers and large load customers | Invenergy, The AES Corporation, Microsoft, Amazon.com, Meta Platforms, Equinix, Digital Realty | Generation, storage and data centre load requests | Submit the requests in the queue |
| Regulators, laboratories and associations | Federal Energy Regulatory Commission, U.S. Department of Energy, North American Electric Reliability Corporation, Lawrence Berkeley National Laboratory, Electric Power Research Institute, American Clean Power Association, Solar Energy Industries Association | Rules, data and standards | Set rules and publish data |
Where value migrates.
In 2026 value sits with engineering firms and study software providers, because operators need extra study capacity quickly. By 2030 it moves toward automation platforms embedded in operator processes, because contracts become multi-year and recurring. By 2034 it settles with developers and large load customers that hold ready sites and secured positions, because the cost of waiting falls on them. Margins hold for providers that operators cannot easily replace and narrow for those selling single studies.
Who Will Win — and Why
The archetypes best positioned to capture value as the shift matures.
Firms whose tools run inside the study workflow of one or more operators.
Firms with trained staff and data to complete studies within set deadlines.
Firms with site control, deposits and permits in place that move through cluster studies first.
Regulatory Landscape
| Jurisdiction | Milestone | Indicative timing | Effect on adoption |
|---|---|---|---|
| United States, federal | Order No. 2023 on cluster studies, deposits, site control and study deadlines | In force | Set the national process for generator interconnection |
| United States, federal | Show-cause proceedings on large load interconnection | In progress | Require operators to propose faster processes for data centres and factories |
| PJM | Reliability Resource Initiative and move to a new Cycle process from spring 2026 | In force | Fast-track selected projects and process the remaining queue in cycles |
| MISO and SPP | Expedited resource adequacy studies for firm capacity | In force | Move about 29 GW and 15 GW of mostly gas projects ahead |
| United States, legislation | Proposed act on environmental review and transmission | Proposed, not enacted | Could speed permitting and widen federal transmission powers |
Investment Signals
The signals converge on speed and readiness. A queue of 2,061 GW with only 53 GW reaching operation in 2025, a median of 61 months to operation and automation pilots at five operators support the case for reform, while staffing, withdrawals and affected system studies limit the pace.
Structural limits show where progress could slow: study staffing, restudies after withdrawals, network upgrade costs and large load surges. The brief therefore tracks four indicators: median time from request to operation, completion rate, share of capacity under signed agreements and automation tools in production use.
Cluster studies at all operators first, then automated tools in production use, then large load processes at regional transmission organisations are the expected order of adoption.
Questions This Brief Answers
Strategic Implications
- Software and engineering providers: sign multi-year contracts with operators, show study time savings and add trained staff.
- Utilities and operators: complete the move to cluster studies, put automation into production and publish data on study times.
- Developers: secure site control early, post deposits only for ready projects and plan for upgrade cost sharing.
- Investors and lenders: back developers with signed agreements and treat withdrawal and restudy risk as the main risk.
- Regulators: set deadlines, cost allocation and large load rules that reduce speculative requests.
"A queue of 2,061 GW is not a pipeline of power plants. The next eight years decide how much of it is ever built."